Project Gigabit, BDUK monthly data, September 2026 More than double the homes and businesses reached since last October. Here is every contract 318,000 homes and businesses reached by Project Gigabit contracts, of 846,770 contracted BDUK, snapshot of 17 September 2026 +167,270 more reached than in October 2025, including Northern Ireland from August (our sum) BDUK, Oct 2025 to Sep 2026 38 contracts in the table, from Cornwall to Cumbria, Scotland and Northern Ireland BDUK, Sep 2026 5 contracts showing 100% built, with North Oxfordshire declared complete in October BDUK; GOV.UK By 17 September 2026, the new networks had reached 318,000 of the 846,770 homes and businesses in Project Gigabit contracts, according to Building Digital UK's monthly table. BDUK calls these premises "built", meaning the new network reaches them. That's more than double the 150,730 in BDUK's first table in October 2025. Five contracts show 100% built: Central Cornwall, North Dorset, North Shropshire, Northumberland and South West Cornwall. North Oxfordshire was declared complete on 13 October 2026. Every contract is ranked below, with how far it has come since last autumn. Built means the network reaches you, so check your address and order when your supplier says you can. Outside Project Gigabit, Openreach's own October 2026 build list shows the main build finished in 2,154 exchange areas, up from 1,383 in March. Key facts, checked 20 October 2026 Who this is for: Households and businesses waiting for full fibre in rural areas, parish councils and community groups following their local build, and anyone who wants to see how the government's broadband programme is going. For how Project Gigabit works, see our Project Gigabit explainer. Direct answer: By 17 September 2026, the new networks had reached 318,000 of the 846,770 homes and businesses in Project Gigabit contracts, BDUK's monthly table shows. That's more than double the 150,730 in October 2025. Homes and businesses reached by all Project Gigabit contracts, month by month Building Digital UK, the government body that runs Project Gigabit, has published this table every month since October 2025. The number reached went up in every edition, rising by 167,270 over 11 months, or about 15,200 a month on average (our sums). That rise includes Northern Ireland's 2,490, which joined the table in August 2026. The September total was 21,230 higher than August's, the second-biggest monthly rise after April. The contracted total has moved too, from 1,002,270 in October 2025 to 846,770 now, mainly because some contracts were redesigned in May 2026. So the number reached is the fairest way to track progress over time. Direct answer: Five contracts show 100% built in BDUK's September 2026 table: Central Cornwall, North Dorset, North Shropshire, Northumberland and South West Cornwall. The government declared North Oxfordshire complete on 13 October 2026. BDUK's contracted figures only count "the initial scope of contracts", and some were made smaller during the year: Central Cornwall went from 9,810 contracted premises to 6,940 in March 2026, and South West Cornwall from 11,140 to 6,400 in April. So 100% means every premises in BDUK's current contracted figure is built. Contracts showing 100% built, plus North Oxfordshire Central Cornwall 6,940 of 6,940 premises built, by Wildanet. 100% in BDUK's September table. North Dorset 6,480 of 6,480 premises built, by Wessex Internet. 100% in BDUK's September table. North Shropshire 3,410 of 3,410 premises built, by Freedom Fibre. 100% in BDUK's September table. Northumberland 3,830 of 3,830 premises built, by GoFibre. 100% in BDUK's September table. South West Cornwall 6,400 of 6,400 premises built, by Wildanet. 100% in BDUK's September table. North Oxfordshire Declared complete on 13 October 2026, four months early, with 3,880 premises. Our North Oxfordshire guide has the villages. Direct answer: Find your area in the chart below. It ranks all 38 contracts by the share of their premises reached so far, with the numbers BDUK published for 17 September 2026. Every Project Gigabit contract, ranked by share built Openreach's "CO" contracts sit lower down. One likely reason: BDUK's first table in October 2025 showed five of the seven call-offs then listed with fewer than 100 premises built. Several were also made bigger during 2026, which lowers their share built. BDUK says "'CO' refers to Type C Call Off contracts". Contracted figures only count "the initial scope of contracts", and BDUK warns its figures "should not be used to assess whether contractual milestones have been met". Our guide to Openreach full fibre upgrades explains what happens when Openreach reaches your street. Two notes for readers checking their area. West Herefordshire and the Forest of Dean are now part of CO3, which doesn't carry their names; GOV.UK says the Forest of Dean was added in September 2026, so it may not show in these figures yet. And North Oxfordshire shows 3,880 of 4,180 here, although the government has declared it complete with 3,880 premises; our North Oxfordshire guide explains. Direct answer: Lincolnshire and East Riding reached the most extra premises between May and September 2026, at 5,720, followed by Cumbria at 4,420. Three Openreach call-offs each added close to 4,000. Fastest movers, May to September 2026 BDUK's total reached was 61,320 higher in September than in May, including Northern Ireland's 2,490, which joined the table in August 2026. As a group, Openreach's eight call-offs added the most of any supplier, going from 32,740 to 54,750 built, 22,010 of the rise, by our sums. Direct answer: Ten companies hold the 38 contracts. Openreach has the most premises under contract, and CityFibre has built the most so far, by our sums from BDUK's table. Built and still to build, by supplier Direct answer: BDUK's table lists one Scottish contract and one in Northern Ireland, while Wales sits inside two Openreach contracts shared with England. The government's progress update gives extra figures for each nation. Scotland, Wales and Northern Ireland Scotland CO6 Rest of Scotland (Openreach): 7,030 of 77,640 built. The government says GoFibre and Openreach contracts in Scotland have reached "More than 5,600 premises". Wales Wales is inside two Openreach contracts shared with England (CO2 and CO3). The government says "around 60,000 premises" in Wales should benefit, with "more than 7,000 premises already reached". Northern Ireland Northern Ireland (Fibrus): 2,490 of 9,330 built. It joined BDUK's table in August 2026. Direct answer: Mostly because suppliers resubmitted data and earlier records were removed, to be re-added later. BDUK says the August changes reflect "updates to underlying administrative data rather than a change in delivery performance". Why some figures went down, and what BDUK said Direct answer: Some areas moved to new suppliers and some contracts were redesigned. In May 2026, for example, CityFibre and BDUK redesigned several contracts after a big rise in commercial building. How the contracts changed in 2026 For Norfolk, GOV.UK says the redesigned contract now covers "around 33,000 premises backed with £61.9 million investment through Project Gigabit". For Nottinghamshire and West Lincolnshire, it says "less public funding is required and the contract is no longer appropriate", and that BDUK is "in discussions with other suppliers" for the few premises not covered by any rollout plans. Direct answer: No. The 318,000 counts homes and businesses reached inside current Project Gigabit contracts. The 1,462,910 is BDUK's official estimate of all premises that have received gigabit-capable coverage through BDUK subsidy since its gigabit programmes began. Two BDUK numbers, measuring different things 318,000 BDUK's monthly table: homes and businesses the new networks reach (BDUK calls them "built"), inside current Project Gigabit contracts. Snapshot of 17 September 2026. 1,462,910 BDUK's official statistics: an estimated total of premises that have received gigabit-capable coverage through BDUK subsidy since its gigabit programmes began, to June 2026. Direct answer: Check the GOV.UK gigabit checker, then the contract page for your area, then the building company's own checker. When it says you can order, choose a provider on that network. Is my home in Project Gigabit? Four checks 1. GOV.UK checker See if gigabit broadband is "available or planned" at your address in England and Wales. 2. Contract page GOV.UK's Project Gigabit contract pages show who is building in your area. 3. Supplier's checker The company building the network knows when your home is ready. 4. Order Choose a provider on that network and book the installation. Built means the new network reaches you; it doesn't switch anyone over. Our address check guide walks you through it, and our guide to missing out when next door has full fibre explains why neighbours can get different answers. Full fibre reached you? See every deal at your address Put in your postcode to see the deals we can find for your home, sorted by price. Prefer to talk it through? Call 0330 122 1223 Direct answer: Keep checking: BDUK reviews providers' plans every four months and is still adding premises to contracts. New gigabit voucher projects closed on 31 August 2026. The government's progress update says that "Between January and July 2026, for example, BDUK added premises to existing contracts covering parts of Essex, Herefordshire and Shropshire", and that it intends to complete its remaining framework awards "by the end of 2027". Meanwhile, our village full fibre playbook sets out the routes still open, and our Starlink guide covers satellite for the hardest-to-reach homes. Direct answer: It may be. Openreach's own build list, updated in October 2026, names 3,519 exchange areas. It says it has finished the main part of its build in 2,154 of them and is building in 1,307 more. The list doesn't include its Project Gigabit work. Openreach's own build list, October 2026: 3,519 exchange areas 1,311 of the listed exchanges marked "Stop-sell Activated", up from 1,072 in March Openreach, Full Fibre Build Programme, October 2026 103 marked "Exchange Exit": exchange buildings Openreach plans to close by 2030 Openreach, Full Fibre Build Programme, October 2026 +771 more exchanges with the main build finished than in March 2026 (our count) Openreach, March and October 2026 As well as its eight Project Gigabit call-offs, Openreach builds full fibre through its own programmes. Its build list covers its "Fibre First Towns, Cities and Boroughs Build Programme as well as Market towns and villages build Programmes", and Openreach says it "doesn't show FTTP deployment related to BDUK". Each line is an exchange area, the patch served by one telephone exchange, which Openreach says covers "a village, small town or part of a larger town or city". You can find yours on Openreach's build map. Two routes to full fibre: Openreach's own build and Project Gigabit Openreach's own build list Project Gigabit So if your exchange is on Openreach's list, full fibre may reach your street without Project Gigabit. Even then, Openreach says some properties are "too difficult or complex to upgrade commercially", but they "may be covered by another one of our programmes or through public funding". Either way, Openreach suggests registering for updates through its Fibre Checker, which follows your own home rather than the exchange as a whole. Direct answer: Openreach now lists 2,154 exchanges where it has finished the main part of its build, up from 1,383 in its March 2026 list. That's 771 more in about seven months, by our count of the two lists. Exchanges where Openreach has finished the main build, and stop-sell, by edition Across Openreach's four lists since June 2025, the number of exchanges with the main build finished has more than tripled, from 688 to 2,154. Stop-sell, where providers can no longer sell new copper services because most premises can get full fibre, is now active in 1,311 of the listed exchanges, 239 more than in March. Openreach's press release gives a bigger total: it says stop-sell will be active in 1,663 exchanges, covering around 16.4 million premises, by 5 November 2026. Our guide to the newest stop-sell list has the latest exchanges. The list is slightly shorter than in March, at 3,519 exchanges rather than 3,525. Six left it: Broxton, Edale, Hamstall Ridware, Hungarton, Masham and Weston Zoyland. And 58 exchanges are listed as "We'll be building in this exchange in the future", 47 of which were listed as "We're building in this area already" in March. Openreach's list doesn't give reasons for changes to individual exchanges, but its build page says: "We don't like changing plans, but from time-to-time we do need to." The 58 exchanges listed for future build, and the six that left the list "We'll be building in this exchange in the future", October 2026 On the March 2026 list, not on the October 2026 list If your exchange has left the list or moved to "in the future", there's still hope. Openreach says that not being on its current plan "doesn't mean we won't come back and build more in the future", and the GOV.UK gigabit checker shows whether gigabit broadband is "available or planned" for your address in England and Wales. Direct answer: Stop-sell means providers can no longer sell new copper broadband and phone services in that exchange, because at least 75% of the premises it serves can get full fibre. Exchange Exit marks exchange buildings Openreach plans to close by 2030, with lines moved to other exchanges. What the labels in Openreach's list mean Finished the main part Build "has been largely completed". Openreach says it "doesn't mean that services will be available from this date, or that services will be available to every premise", and more may follow. Building already, soon or in the future Where Openreach is in its build. "Soon" means "with services available in the next 12 months"; "in the future" comes with no date in the list. Stop-sell activated "Stop Sell is triggered when 75% of premises served by an exchange can access Full Fibre broadband." Providers then can't sell new copper-based broadband and phone services there. Exchange Exit An exchange building Openreach plans to close. Its programme "covers 107 exchange sites which Openreach plan to fully close by 2030", with lines moved to other exchanges. Its list marks 103, the number its consultation papers call "the 103 priority exchanges". If you're on a copper line in a stop-sell exchange but can't get full fibre yet, Openreach says customers in that position "won't be impacted and can stay on their existing copper-based service until Full Fibre does become available". The separate move of landlines to digital phone lines is covered in our copper switch-off guide. Direct answer: Ofcom says 89% of UK homes could get gigabit-capable broadband in January 2026. Project Gigabit is aimed at homes and businesses unlikely to be reached by commercial rollout alone, towards the government's 99% target for 2032. Where the UK stands on gigabit broadband The government's progress update puts it as "more than 88% of homes and businesses", with "approximately 4 million premises remaining without coverage". Ofcom's 89% figure counts homes, while the government's figure covers homes and businesses together. Openreach says its own full fibre network "is available to more than 23.5 million premises", and its plan is for "25 million homes and businesses by 2026". In summary Alex's closing thought I love this table, because it turns a national promise into something you can see happening in your own county, month after month. More than doubling the number of homes and businesses reached since last October is real progress, and Openreach's call-offs added the most of any supplier this summer. Openreach's own list adds to the good news, with the main build finished in 771 more exchange areas since March. If your area is on either list, check your address every few months and order when your supplier says you can. We'll refresh this page each time BDUK publishes a new edition. Project Gigabit Check your address Not in a contract yet? Share it with your parish council, village group or local councillor, so people can see how their area is doing. You are welcome to quote and link to this article. Most figures are Building Digital UK data under the Open Government Licence. Please credit BDUK for that data, Openreach for its build list figures and BroadbandSwitch.uk for the charts and calculations, and link to this page. In a sentence: Building Digital UK's September 2026 table shows the new networks had reached 318,000 of the 846,770 homes and businesses in 38 Project Gigabit contracts by 17 September 2026, up from 150,730 in October 2025, with five contracts at 100% built and North Oxfordshire declared complete on 13 October 2026. It is "the government programme to bring gigabit-capable broadband to homes and businesses unlikely to be reached through commercial, privately-funded rollout alone", in the government's words. Building Digital UK runs it. 318,000 homes and businesses inside current contracts, which BDUK counts as "built", by its snapshot of 17 September 2026. Separately, BDUK's official statistics estimate that 1,462,910 premises have received gigabit-capable coverage through BDUK subsidy since its gigabit programmes began, to June 2026. Central Cornwall, North Dorset, North Shropshire, Northumberland and South West Cornwall show 100% built in BDUK's September 2026 table. The government declared North Oxfordshire complete on 13 October 2026. BDUK says it tracks "the number of contracted premises to which the supplier has delivered a gigabit-capable connection". Put simply, the new network reaches the premises. BDUK's figures run behind what's happening on the ground, because there is "a variable time lag" before data reaches it. The building company's own checker is the best guide to when you can order. Mostly because suppliers resubmitted data and earlier records were removed, to be re-added later. BDUK says the August 2026 changes "reflect updates to underlying administrative data rather than a change in delivery performance". Put your postcode into the GOV.UK gigabit checker, which covers England and Wales, then look at GOV.UK's Project Gigabit contract pages to see who is building in your area. Openreach has the most premises under contract, at 357,930 across eight call-offs, which BDUK calls "Type C Call Off contracts" and numbers CO1 to CO8. CityFibre has the most built so far, at 78,950, by our sums from BDUK's September 2026 table. No. Openreach says its build list "doesn't show FTTP deployment related to BDUK", which runs Project Gigabit. Its October 2026 list names 3,519 exchange areas, and says the main part of the build is finished in 2,154 of them. BDUK's table shows CO6 Rest of Scotland at 7,030 of 77,640 built, and Northern Ireland at 2,490 of 9,330 built, in September 2026. Not for a new project. The Gigabit Broadband Voucher Scheme closed to new voucher project submissions on 31 August 2026. The government's target is gigabit-capable broadband for 99% of homes and businesses by 2032. The GOV.UK checker is next updated in February 2027, and your supplier's own checker may be more up to date. Written by Dr Alex J. Martin-Smith, Founder of BroadbandSwitch.uk (LinkedIn). Reviewed by Adrian James, Broadband Editor. Published 20 October 2026. We read all 12 of BDUK's monthly tables on 20 October 2026 and checked our copy of every row against the live pages. We also read BDUK's official statistics, the September 2026 progress update, the GOV.UK contract pages quoted, the GOV.UK checker and voucher pages, and Ofcom's coverage figures. For Openreach's own build, we counted every exchange in its build lists for June 2025, October 2025, March 2026 and October 2026, and read its build map page, its press releases of 27 July and 8 October 2026 and its Exchange Exit page. Percentages, sums and changes are our own calculations from BDUK's and Openreach's published figures. BDUK rounds its figures to the nearest 10. This is general information, not professional advice. Corrections are logged publicly.Project Gigabit, Contract by Contract: What Has Been Built by September 2026
How much of Project Gigabit has been built so far?
Which Project Gigabit contracts show 100% built?
How is my area's contract doing?
Which contracts moved fastest this summer?
Who is building it?
What about Scotland, Wales and Northern Ireland?
Why did some numbers go down?
How have the contracts changed this year?
Is 318,000 the same as the 1.46 million I've seen elsewhere?
Is my home in Project Gigabit, and can I order?
What if my home isn't in any contract?
Is Openreach building full fibre in my area outside Project Gigabit?
Finished the main part of the build
Building there already
Building in the futureHow has Openreach's build list changed since March 2026?
What do stop-sell and Exchange Exit mean on Openreach's list?
How does this fit with UK gigabit coverage?
Keep going: more on Project Gigabit and rural full fibre
Share this article
Cite this page
Martin-Smith, A. J. (2026, October 20). Project Gigabit, contract by contract: What has been built by September 2026. BroadbandSwitch.uk. https://broadbandswitch.uk/insights/project-gigabit-progress-september-2026/ Frequently asked questions
What is Project Gigabit?
How many homes and businesses has Project Gigabit reached so far?
Which Project Gigabit contracts show 100% built?
What does "built" mean in BDUK's table?
Does built mean I can order full fibre?
Why did some Project Gigabit numbers go down?
Is my home in a Project Gigabit contract?
Which supplier is building the most Project Gigabit premises?
Is Openreach's own full fibre build list part of Project Gigabit?
What is Project Gigabit doing in Scotland and Northern Ireland?
Can I still get a gigabit broadband voucher?
When will Project Gigabit reach my home?
References
Project Gigabit Progress: Every Contract, September 2026
Written by Alex Martin-Smith (LinkedIn) • Reviewed by Adrian James (LinkedIn)
Last reviewed: 20 October 2026
Quick summary: BDUK's September 2026 data shows 318,000 premises built across 38 Project Gigabit contracts. See every contract, the five at 100% and how to check yours.

OctNovDecJanFebMarAprMayJunJulAugSep
20252026
OpenreachCityFibreQuickline CommunicationsFibrusWessex InternetWildanetConnect FibreGigaclearGoFibreFreedom Fibre
Central CornwallWildanet
100%
6,940 of 6,940
North DorsetWessex Internet
100%
6,480 of 6,480
North ShropshireFreedom Fibre
100%
3,410 of 3,410
NorthumberlandGoFibre
100%
3,830 of 3,830
South West CornwallWildanet
100%
6,400 of 6,400
North OxfordshireGigaclear
93%
3,880 of 4,180
DurhamGoFibre
91%
4,050 of 4,440
New ForestWessex Internet
84%
10,710 of 12,730
Bedfordshire, Northamptonshire and Milton KeynesCityFibre
82%
4,820 of 5,890
CambridgeshireCityFibre
79%
14,330 of 18,230
South YorkshireQuickline Communications
73%
9,740 of 13,290
South OxfordshireGigaclear
71%
3,640 of 5,120
CumbriaFibrus
71%
37,750 of 53,540
West and Parts of North YorkshireQuickline Communications
69%
20,000 of 28,950
Bucks, Herts and East of BerksCityFibre
67%
4,100 of 6,090
East GloucestershireGigaclear
62%
2,190 of 3,550
Lincolnshire and East RidingQuickline Communications
53%
24,770 of 46,970
SuffolkCityFibre
50%
19,150 of 38,350
North East StaffordshireConnect Fibre
49%
2,950 of 5,960
Leicestershire and WarwickshireCityFibre
48%
10,840 of 22,480
South WiltshireWessex Internet
45%
8,410 of 18,790
NorfolkCityFibre
42%
13,800 of 32,670
Northern North YorkshireQuickline Communications
37%
12,850 of 34,490
CO2 Devon, Mid Wales and South East WalesOpenreach
32%
13,060 of 41,140
Dorset and South SomersetWessex Internet
31%
5,780 of 18,510
Cornwall and Isle of ScillyWildanet
31%
4,440 of 14,430
KentCityFibre
30%
2,610 of 8,750
DerbyshireConnect Fibre
28%
3,640 of 12,880
East and West SussexCityFibre
28%
3,580 of 12,760
Northern IrelandFibrus
27%
2,490 of 9,330
CO1 Lancashire, West Berkshire, Staffordshire, Surrey, Hertfordshire, Wiltshire and GloucestershireOpenreach
26%
15,410 of 60,180
HampshireCityFibre
19%
5,720 of 29,420
CO4 South Devon, Mid Devon and North SomersetOpenreach
19%
7,110 of 37,110
CO5 Essex and North East EnglandOpenreach
14%
4,860 of 35,300
CO6 Rest of ScotlandOpenreach
9%
7,030 of 77,640
CO7 WorcestershireOpenreach
8%
1,810 of 22,980
CO3 North Herefordshire, North Wales, Shropshire and South West WalesOpenreach
7%
4,480 of 65,120
CO8 CheshireOpenreach
5%
990 of 18,460
Lincolnshire and East RidingQuickline Communications: 19,050 in May, 24,770 in September
+5,720
CumbriaFibrus: 33,330 in May, 37,750 in September
+4,420
CO5 Essex and North East EnglandOpenreach: 880 in May, 4,860 in September
+3,980
CO4 South Devon, Mid Devon and North SomersetOpenreach: 3,150 in May, 7,110 in September
+3,960
CO2 Devon, Mid Wales and South East WalesOpenreach: 9,210 in May, 13,060 in September
+3,850
West and Parts of North YorkshireQuickline Communications: 16,310 in May, 20,000 in September
+3,690
BuiltContracted, not yet built
Openreach8 contracts
54,750 of 357,930
CityFibre9 contracts
78,950 of 174,640
Quickline Communications4 contracts
67,360 of 123,700
Fibrus2 contracts
40,240 of 62,870
Wessex Internet4 contracts
31,380 of 56,510
Wildanet3 contracts
17,780 of 27,770
Connect Fibre2 contracts
6,590 of 18,840
Gigaclear3 contracts
9,710 of 12,850
GoFibre2 contracts
7,880 of 8,270
Freedom Fibre1 contract
3,410 of 3,410
May 2026
BDUK removed 420 premises from Bedfordshire, Northamptonshire and Milton Keynes and 2,140 from North Shropshire, "To be re-added at a later date". North Shropshire was back to 3,410 of 3,410 by July.
June 2026
310 premises taken out of North Dorset. It was back to 6,480 of 6,480 by September.
August 2026
6,740 premises taken out across seven contracts (our sum), the largest being 4,220 from CO1. BDUK: "These revisions reflect updates to underlying administrative data rather than a change in delivery performance."
September 2026
Durham fell to 4,050 during an "in-progress change request from supplier", and Hampshire to 5,720 "due to missing submission from December 2024".
Feb 2026
Cheshire moves to Openreach as a new call-off, CO8: "around 18,500 hard-to-reach premises".
Apr 2026
West Herefordshire is added to Openreach's CO3.
May 2026
CityFibre and BDUK redesign several contracts after more commercial building, and end the Nottinghamshire and West Lincolnshire contract.
Aug 2026
Northern Ireland joins BDUK's monthly table.
Sep 2026
The Forest of Dean is added to CO3.
13 Oct 2026
North Oxfordshire is declared complete, four months early.
→
→
→
Compare at my postcode →
2,154 (61%)
1,307 (37%)
58 (2%)
Finished the main part of the buildStop-sell activated
June 2025October 2025March 2026October 2026
AghadoweyAughnacloyBaillies MillsBallinamallardBallykinlerBardneyBelcooBelfast FortwilliamBellarenaBelleekBlanefieldBlewburyBuxtedCarryduffComberCrossgarCrossmaglenCushendallDervockDownpatrickDraperstownDrumboDrumquinDundrodDundrumEglintonFintonaFlorencecourtGilfordGlarryfordHedinghamHelens BayIrvinestownIslandmageeKillinchyKillyleaghKirkconnelMillisleMoyNewtownbutlerNewtownhamiltonRasharkinRichhillRomsleyRosleaRostrevorSaintfieldSeafordeSilverdaleSomertonStoneyfordStrangfordTemplepatrickWansfordWarrenpointWhiteheadWidemouth BayWoldingham
BroxtonEdaleHamstall RidwareHungartonMashamWeston Zoyland
Homes able to get gigabit-capable broadband, January 2026 (Ofcom)
89%
Homes and businesses, "more than 88%" (GOV.UK, quoting Ofcom)
88%+
Government target by 2032, homes and businesses
99%